Title: A cash flow-based approach for assessing expansion options stemming from project modularity

Authors: Franco Caron; Monia Comandulli

Addresses: Department of Management, Economics and Industrial Engineering, Politecnico di Milano, Piazza Leonardo da Vinci 32, 20133 Milan, Italy ' ABB, Process Automation Division, Via Luciano Lama 33, 20099 Sesto San Giovanni (MI), Italy

Abstract: Investment projects in the electricity production industry face a dynamic and complex context. Project's modularity, through the breakdown of the project output into a set of small identical independent units, enables a stepwise investment policy and a partial self-financing of the project, so improving project's flexibility. As a consequence, the construction phase may be described as a sequence of expansion options, each option allowing for deciding if and when to build the next production unit. Firstly, this paper proposes a model of the project cash flow aiming at evaluating and comparing alternative configurations of a production plant, considering both the construction and operation phases. Secondly, an expanded net present value model, based on Monte Carlo simulation, has been developed in order to estimate the value for the project of the expansion options stemming from project's modularity. The model has been applied to a case concerning a III+ generation modular nuclear power plant.

Keywords: large engineering projects; modularity; real options analysis; ROA; Monte Carlo simulation; modular NPP; nuclear power plants; expansion options; project cash flow; nuclear energy; investment projects; electricity production; project flexibility; expanded NPV; net present value.

DOI: 10.1504/IJPOM.2014.059741

International Journal of Project Organisation and Management, 2014 Vol.6 No.1/2, pp.157 - 178

Received: 31 Jul 2010
Accepted: 19 Aug 2011

Published online: 24 May 2014 *

Full-text access for editors Full-text access for subscribers Purchase this article Comment on this article