Title: Project managers' capacity-planning practices for infrastructure projects in Qatar: a multiple-case study

Authors: Ojo Emmanuel Opeyemi; Michael Neubert

Addresses: Oj&Fas Incorporated, 190 Walgrove Terrace, Calgary Alberta, T2X 4E7, Canada ' International School of Management (ISM), 17 Boulevard Raspail, Paris, France

Abstract: Infrastructure project delays and cost overrun are often caused by ineffective use of organisational skills, processes, and resources. Cost overrun and schedule delay in Qatari have had damaging effects on the national economy. The purpose of this study was to explore the perceptions of project managers regarding how they utilise capacity-planning practices to manage government-funded projects in Qatar. This study was framed by three conceptual models developed by Gill to outline capacity management needs within a construction company: the time horizon model, individual-organisation-industry levels model, and capacity development across components model. Data were collected from semistructured interviews with eight participants. Fifteen themes emerged through thematic analysis of textual data and cross-case synthesis analysis, across five conceptual categories: resources to meet performance capacity, knowledgeable and skilful staff, short- and long-term planning strategy, cost overrun issue, and time management. Findings may promote timely completion of projects, and improve the economy of Qatar.

Keywords: capacity planning; project management; project management theory; infrastructure project delay; schedule delay; cost overrun; GCC; Middle East; Qatar; capacity-planning concept and models.

DOI: 10.1504/IJPOM.2021.119517

International Journal of Project Organisation and Management, 2021 Vol.13 No.4, pp.379 - 408

Received: 14 Apr 2020
Accepted: 25 Nov 2020

Published online: 08 Dec 2021 *